Life Science | Bavarian Nordic

Building management system for Bavarian Nordic’s filling facility
In parallel with the construction project, Init built the building management system for Bavarian Nordic’s new filling facility
In 2018, Bavarian Nordic began construction of a 3,200 m2 fill-finish facility in extension of its existing large-scale vaccine manufacturing facility in Denmark. Equipped with isolator technology, and with large-scale lyophilisation, labelling and packaging line, the new facility will further improve Bavarian Nordic’s ability to manufacture multiple products, e.g. smallpox vaccine, at commercial scale. The new facility has been designed with a potential annual capacity of up to 40 million doses of liquid vaccines and 8 million doses of freeze-dried vaccines.
Aspiration
Efficient control of all building automation
Solution
Advanced building management system
Result
Consistent climate conditions
Reach out
for more information

Related

Produktion
FORCE Technology
Danske FORCE Technology har bygget verdens største lukkede loop til at kalibrere flowmålere. Init, som er FORCE Technologys automationspartner på projektet, har stået for al programmering af automationssystemet Læs mere

Akva- & Agrikultur
Danish Agro
Ved at opgradere kontrolsystemet på deres foderproduktion til Inits Agro 3000 løsning har Danish Agro øget fleksibilitet og leveringssikkerhed. Læs mere