Control system upgrade lifts furnace SI5-5 to a new level
Init helped Elkem Solar upgrade the control system on furnace SI5-5 to System 800xA on virtual servers, completing the switchover within a single shutdown and giving operators better decision support.
Elkem Solar produced high-purity silicon for solar cells at Fiskaa in Kristiansand, a process that demands precise control and stable furnace operation.
To keep the control system on furnace SI5-5 secure, up to date and fit for the future, Elkem Solar engaged Init Kristiansand (then Necto) in 2016–2017 to carry out a complete upgrade.
ASPIRATION
A secure, modern control system without disrupting production
SOLUTION
A complete upgrade, within a single shutdown
RESULT
Connecting people, process and equipment
Reach out
for more information
Related
Energy
SAREN Energy BIO-EL
Init migrated SAREN Energy BIO-EL’s waste-to-energy plant to the latest 800xA version, with a better HMI and cyber security in focus. Read more
Manufacturing
Elkem Salten
Init delivered robust temperature monitoring for a smelting furnace relining at Elkem Salten, built on ABB System 800xA and M-System R3. Read more
Manufacturing
Elkem Salten
Init gave Elkem Salten remote access to 470 flow meters via System 800xA, improving leak detection and enabling predictive maintenance. Read more